AMEC CIVIL ENGINEERING LTD V SECRETARY OF STATE FOR TRANSPORT

Court of Appeal
[2005] EWCA Civ 291
May LJ, Rix LJ and Hooper LJ
March 2005

A decision made under clause 66 of the Institute of Civil Engineers (ICE) conditions of contract has to be made independently and honestly but will not be procedurally unfair if it does not comply with the rules of natural justice. The term "dispute or difference" in clause 66 should be given an inclusive interpretation.

The appellants were engineering contractors who had been engaged by the Secretary of State for Transport, the defendant, to perform major renovation works to a viaduct. Deficiencies in the structure of the viaduct became apparent approximately 6 months before the 6 year limitation period was to expire. It was thought that these defects could be traced to problems with a structural component (the roller bearings) which the appellant had designed and provided as part of the renovations. Though this could not be determined conclusively without a detailed investigation.

The contract was governed by the Institution of Civil Engineers (ICE) standard conditions of contract and the mechanism for disputes is dealt with at clause 66 of these conditions. Clause 66 specifies that a dispute or difference should be referred in the first instance to an engineer for a decision and that after either the receipt of the written decision of the engineer or the passing of 3 months without a response, it can be referred to arbitration.

After the defects in the structure of the viaduct (and the roller bearings) became apparent, the defendant referred the so-called dispute to an engineer for a decision. The decision was made within 7 days and stated that the roller bearings provided and installed by the appellant were not in accordance with the contract. Immediately thereafter, the defendant asked the appellant whether they accepted this decision and, in the absence of any response from the appellant, the defendant gave notice of arbitration, pursuant to clause 66.

The appellants argued that there was no valid dispute or difference within the meaning of the phrase in clause 66, capable of being referred to the engineer; and, secondly, that even if there was a valid dispute at the time of referral, the decision reached by the engineer was not valid for procedural reasons. The reasons given included the fact that the appellant had not been given the opportunity to make submissions to the engineer before he reached his decision and also that the engineer made his decision with undue speed. There was a third ground of appeal relating to the scope of the arbitrator's jurisdiction. Both Mr Robert Akenhead QC (the appointed arbitrator) and Jackson J at the Technology and Construction Court dismissed all three of these arguments.

In relation to the first of the appellant's arguments, it was held that there was a valid dispute which therefore was capable of being referred to an Engineer for a decision. It was noted that the question of what constitutes a "dispute" has been the subject of much litigation but that, nonetheless, there is no clear definition of the term for the purposes of arbitration clauses. In particular it was noted that inclusion of the word "difference" along with "dispute" in clause 66 suggested that it should not be restricted to a strict legalistic definition but rather that a broader meaning should be given to the phrase. May LJ also noted that commercial sense suggests that the clause should not be interpreted in such a narrow way as to prevent the parties' commencing arbitration proceedings on time.

With regard to the second argument, It was held that the conduct of the engineer's decision and the arbitration had not been procedurally unfair and that accordingly, their decisions remain valid. It was noted in particular that whilst an engineer giving a decision on a referral pursuant to clause 66 must act independently and honestly, he is not obliged to adhere to rules of natural justice. There is no procedure specified in the ICE conditions of contract as to how an engineer should conduct his decision and the engineer is not expected to act in a judicial manner in making his decision. The third argument was dismissed as being without merit and it was held that the scope of the arbitration was the whole matter, and not just those limited aspects on which the engineer had given a decision.